4D v14.3DELAY PROCESS |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4D v14.3
DELAY PROCESS
DELAY PROCESS
DELAY PROCESS delays the execution of a process for a number of ticks (1 tick = 1/60th of a second). During this period, process does not take any processing time. Even though the execution of a process may be delayed, it is still in memory. If the process is already delayed, this command delays it again. The parameter duration is not added to the time remaining, but replaces it. Therefore pass zero (0) for duration if you no longer want to delay a process. If the process does not exist, the command does nothing. Note: You cannot use this command to assign a stored procedure on the server machine from a client machine (process<0). See example in Record Locking. See example for the command Process number. |
PROPERTIES
Product: 4D
HISTORY
Created: < 4D v6 SEE ALSO ARTICLE USAGE
4D Language Reference ( 4D v12.4) Parent of : DELAY PROCESS ( 4D v14 R3) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||